Schedule
Jan 1, 2021 - Dec 31, 2021 | 265 days
-
1
Feb 26 - Mar 5, 2021Complete
-
Not Started -
In Progress -
Completed
-
TaskStart/End DateDurationGroupStatus
-
Pre-Con LaunchJan 27 - Apr 30, 202181 daysComplete -
ConsultantsFeb 26 - Oct 27, 2021173 daysComplete -
ArchitectureJul 16 - Nov 11, 202184 days4%Concept DesignJul 16 - Aug 16, 202121 daysSchematic DesignAug 16 - Sep 6, 202115 daysDesign DevelopmentSep 22 - 30, 20216 daysConstruction DrawingsSep 30 - Nov 11, 202130 days -
EstimatingSep 6 - Dec 31, 202184 days0% -
PermittingNov 4 - Dec 31, 202141 daysNot started
14 Followers | Unfollow
Details
Status
Start Date
End Date
Duration
Dependencies
Predecessors
Add a Predecessor
16
Create Site plan for pre-screening
FF + 2
18
Obtain homeowner approval to proceed based on results of prescreen
ES + 0
Successors
Add a Successor
21
Coordinate modifications to concept plan, schedule and hold concept review meeting with homeowner
ES + 0
LP
Lauren Platt
No task selected
-
Not Started -
In Progress -
Completed
-
TaskStart/End DateDurationGroupStatus
-
PurchasingJan 27 - Apr 30, 202181 daysComplete -
Project CommencementFeb 26 - Oct 27, 2021173 daysComplete -
FoundationApr 19 - Jul 16, 202164 daysComplete -
MechanicalsApr 19 - Jul 16, 202164 daysComplete -
Interior FinishesApr 28 - Sep 21, 2021105 days2%FlooringApr 28 - Sep 10, 202197 daysDrywall (Regular)Aug 16 - Sep 6, 202121 daysCabinetsSep 22 - 30, 20215 daysFinish Carpentry (Regular)Sep 30 - Nov 11, 20214 daysInterior PaintSep 30 - Nov 11, 20211 dayInstall Interior Finish TrimsSep 30 - Nov 11, 20219 daysFit and Finish FinalsSep 30 - Nov 11, 20219 days -
Site DevelopmentMay 5 - May 17, 20218 daysComplete -
FramingJun 1 - Aug 17, 202155 daysNot started -
Exterior FinishesJul 8 - Aug 18, 202129 daysNot started -
DeliverySep 17 - 30, 20219 daysNot started
14 Followers | Unfollow
Details
Status
Start Date
End Date
Duration
Dependencies
Predecessors
Add a Predecessor
9
Builder signed contract
ES + 0
Successors
Add a Successor
11
Order temp toilet and handwash
ES + 0
12
Order Homebound signage
ES + 0
13
Order temp fencing
ES + 0
No task selected